City of Piedmont - 2014 Pavement Rehabilitation Project

Coastland performed construction management and inspection services on this project which included mill and fill overlay, sidewalk and curb/gutter work, construction of a concrete pad, ADA ramp reconstruction, tree removal and striping. The project schedule was accelerated in order to complete the construction prior to the 2014 school year. Final construction costs were under the original construction budget and Construction management services were 20% under the budgeted amount. This is part of an annual program Coastland has assisted the City with for several years.